IN PHOTOS: Borivali–Virar 5th & 6th line project work takes shape

Updated On: 17 November, 2025 06:54 PM IST | Divya Nair

Work on Mumbai’s ambitious Borivali–Virar 5th & 6th line project, designed to separate suburban and long-distance train operations on the crowded Western Railway corridor, is steadily taking shape (PICS/NIMESH DAVE)  

Work on Mumbai’s ambitious Borivali–Virar 5th & 6th line project, designed to separate suburban and long-distance train operations on the crowded Western Railway corridor, is steadily taking shape (PICS/NIMESH DAVE)
 

1/6

Work on Mumbai’s ambitious Borivali–Virar 5th & 6th line project, designed to separate suburban and long-distance train operations on the crowded Western Railway corridor, is steadily taking shape (PICS/NIMESH DAVE)  
<p>The Rs 2184-crore project, part of MUTP&ndash;III A, promises to add 26 km of dedicated suburban tracks between Borivali and Virar, easing congestion and improving punctuality for over 35 lakh daily commuters</p>

2/6

The Rs 2184-crore project, part of MUTP–III A, promises to add 26 km of dedicated suburban tracks between Borivali and Virar, easing congestion and improving punctuality for over 35 lakh daily commuters

<p>However, land disputes, environmental restrictions, and legal delays has kept construction scattered and slow</p>

3/6

However, land disputes, environmental restrictions, and legal delays has kept construction scattered and slow

<p>&ldquo;There was even a stay on one major bridge, which we managed to get vacated only recently,&rdquo; an MRVC official had earlier informed mid-day.com. &ldquo;We&rsquo;re clearing every hurdle, but progress remains challenging&rdquo;</p>

4/6

“There was even a stay on one major bridge, which we managed to get vacated only recently,” an MRVC official had earlier informed mid-day.com. “We’re clearing every hurdle, but progress remains challenging”

<p>Officials said the detailed estimate has been sanctioned, and drone surveys have finalised the alignment. Bridge drawings (GADs) are approved, and the Design Development Consultant is finalising designs. Work has begun on two key bridges, while tenders for earthwork between Dahisar and Vasai Road have been invited</p>

5/6

Officials said the detailed estimate has been sanctioned, and drone surveys have finalised the alignment. Bridge drawings (GADs) are approved, and the Design Development Consultant is finalising designs. Work has begun on two key bridges, while tenders for earthwork between Dahisar and Vasai Road have been invited

<p>However, the pace remains sluggish due to pending land acquisition and environmental clearances. Of the 1.81 hectares of private land required, 1.40 ha has been acquired; the rest is locked in litigation. Another 13.62 hectares of salt pan land remains under complex acquisition and environmental review</p>

6/6

However, the pace remains sluggish due to pending land acquisition and environmental clearances. Of the 1.81 hectares of private land required, 1.40 ha has been acquired; the rest is locked in litigation. Another 13.62 hectares of salt pan land remains under complex acquisition and environmental review

Photo of Day

Breaking barriers and building pyramids — Women power in action!

Breaking barriers and building pyramids — Women power in action!

Sashastra Seema Bal’s (SSB) Daredevils team performs during rehearsals for the Republic Day Parade, in New Delhi. PIC/PTI

Advertisement