Updated On: 28 December, 2025 02:42 PM IST | ronak mastakar
Railway officials and contract workers carry out work to install a new railway line during a Jumbo Block between Kandivali and Borivali railway stations in Mumbai on December 28, 2025. (Pics/Satej Shinde)

1/10

2/10
Mumbai commuters brace for disruption as Western Railway (WR) announces the cancellation of 80 local trains daily starting December 21.
ADVERTISEMENT

3/10
To carry out the work in connection with the sixth line on Kandivali and Borivali section, a block of 30 days will be undertaken from the night of December 20th/21st and will continue up to January 18.

4/10
WR`s chief public relations officer Vineet Abhishek said the work involves track slewing and insertion and removal of multiple crossovers at Kandivali and Borivali.
ADVERTISEMENT

5/10
Major works of the engineering, signalling and overhead equipment will be carried out, which will impact train operations.

6/10
Consequently, some suburban, passenger and mail/express trains will be affected.
ADVERTISEMENT

7/10
During the period from December 20th/21st to December 25th/26th, the block will be operated from 11 pm to 04:30 am. Due to the block and suspension of fifth line, some suburban services will remain cancelled.

8/10
Amid the operational work that will be carried out by the authorities, the fifth line of the WR will remain suspended for passenger trains running during the block.
ADVERTISEMENT

9/10
While the Western Railways have also affirmed that there will be speed restrictions imposed on other lines that will ultimately delay the travel time.

10/10
All trains working on the fifth line i.e mail/express and suburban trains will be operated on fast line between Andheri/Goregaon and Borivali.