Home / Mumbai / Mumbai News / Photos / IN PHOTOS: After 7 years, Ghatkopar Metro’s elevated deck finally takes shape

IN PHOTOS: After 7 years, Ghatkopar Metro’s elevated deck finally takes shape

Updated On: 08 January, 2026 01:26 PM IST | Tarun Verma

Mid-day impact: Following seven years of relentless follow-ups by mid-day, the elevated deck on the Mumbai Metro end of Ghatkopar station is inching close to reality (Pics/Rajendra B Aklekar)

Mid-day impact: Following seven years of relentless follow-ups by mid-day, the elevated deck on the Mumbai Metro end of Ghatkopar station is inching close to reality (Pics/Rajendra B Aklekar)

1/13

Mid-day impact: Following seven years of relentless follow-ups by mid-day, the elevated deck on the Mumbai Metro end of Ghatkopar station is inching close to reality (Pics/Rajendra B Aklekar)
<p><strong>DISASTER IN WAITING</strong></p>
<p>August 30, 2019: The station`s upgrade was spurred by a <a href="https://www.mid-day.com/mumbai/mumbai-news/article/Mumbai--Next-disaster-is-arriving-on-platform-No.1-at-Ghatkopar-railway-station-21636166">2019 mid-day front-page</a> report, promting action from former MP Manoj Kotak and then-railway minister Piyush Goyal. The first story that started it all</p>

2/13

DISASTER IN WAITING

August 30, 2019: The station`s upgrade was spurred by a 2019 mid-day front-page report, promting action from former MP Manoj Kotak and then-railway minister Piyush Goyal. The first story that started it all

<p><strong>WORK BEGINS, BUT SAFETY CONCERNS RAISED</strong></p>
<p>June 23, 2022: MRVC launched a seven-point upgrade plan with new FOBs, an elevated deck and a skywalk, but barricades <a href="https://www.mid-day.com/mumbai/mumbai-news/article/mumbai-ghatkopar-station-upgrade-work-begins-but-commuters-call-it-dangerous-and-life-threatening-23232686">narrowed platforms</a>, triggering safety concerns during peak hours</p>

3/13

WORK BEGINS, BUT SAFETY CONCERNS RAISED

June 23, 2022: MRVC launched a seven-point upgrade plan with new FOBs, an elevated deck and a skywalk, but barricades narrowed platforms, triggering safety concerns during peak hours

<p><strong>PLATFORM SPACE RECLAIMED</strong></p>
<p>August 11, 2022: Barricades were later pushed back, freeing <a href="https://www.mid-day.com/mumbai/mumbai-news/article/at-ghatkopar-station-passengers-get-back-their-platform-space-23240390?lifestyle-culture-article-breakingnews">platform space</a> and easing risks flagged by mid-day. MRVC said work amid heavy footfall remains challenging, with completion expected by 2025</p>

4/13

PLATFORM SPACE RECLAIMED

August 11, 2022: Barricades were later pushed back, freeing platform space and easing risks flagged by mid-day. MRVC said work amid heavy footfall remains challenging, with completion expected by 2025

<p><strong>CROWD SURGE DUE TO METRO DISRUPTION</strong></p>
<p>December 15, 2022: A metro cancellation caused a <a href="https://www.mid-day.com/mumbai/mumbai-news/article/mumbai-such-massive-crowd-may-lead-to-stampede-23260670">stampede</a>-like situation on the railway FOB, emphasising the need to fast-track upgrade. Commuters called for better Metro-railway integration and more Metro coaches to manage crowds</p>

5/13

CROWD SURGE DUE TO METRO DISRUPTION

December 15, 2022: A metro cancellation caused a stampede-like situation on the railway FOB, emphasising the need to fast-track upgrade. Commuters called for better Metro-railway integration and more Metro coaches to manage crowds

<p><strong>BREATHING SPACE GAINED</strong></p>
<p>March 10, 2023: A redundant <a href="https://www.mid-day.com/mumbai/mumbai-news/article/mumbai-commuters-get-some-breathing-space-in-busy-ghatkopar-station-23274414?technology-article-breakingnews">staircase</a> on Platform No.1 was demolished, creating more space after mid-day`s 2019 report. The upgrade was progressing to address the high passenger dnsity exacerbated by Metro connectivity</p>

6/13

BREATHING SPACE GAINED

March 10, 2023: A redundant staircase on Platform No.1 was demolished, creating more space after mid-day`s 2019 report. The upgrade was progressing to address the high passenger dnsity exacerbated by Metro connectivity

<p><strong>FUNDING SECURED, WORK PROGRESSES</strong></p>
<p>April 21, 2023: MUTP-3A funding enabled <a href="https://www.mid-day.com/mumbai/mumbai-news/article/mumbai-ghatkopar-station-upgrade-can-proceed-full-steam-ahead-23282094">full-scale work</a>, with Phase 1 on the east side targeted for completion by late 2023 and further phases already funded</p>

7/13

FUNDING SECURED, WORK PROGRESSES

April 21, 2023: MUTP-3A funding enabled full-scale work, with Phase 1 on the east side targeted for completion by late 2023 and further phases already funded

<p><strong>PHASE 1 COMPLETED</strong></p>
<p>December 29, 2023: <a href="https://www.mid-day.com/mumbai/mumbai-news/article/mumbai-ghatkopar-upgrade-phase-1-completed-23327209">Phase 1</a> was completed with a 12-metre-wide, 75-metre-long FOB, and a 15-metre-wide, 47-metre-long east deck, opened to the public. However, commuters noted the lack of direct Metro connectivity, a priority for phase 2</p>

8/13

PHASE 1 COMPLETED

December 29, 2023: Phase 1 was completed with a 12-metre-wide, 75-metre-long FOB, and a 15-metre-wide, 47-metre-long east deck, opened to the public. However, commuters noted the lack of direct Metro connectivity, a priority for phase 2

<p><strong>METRO RELATED CROWDING ISSUES</strong></p>
<p>July 3, 2024: Metro network delay caused a crowd surge on railway FOB, with railway officials blaming Metro`s management. Phase 2 work near the Metro station was set to resume post-monsoon, with calls for Metro to increase coach numbers</p>

9/13

METRO RELATED CROWDING ISSUES

July 3, 2024: Metro network delay caused a crowd surge on railway FOB, with railway officials blaming Metro`s management. Phase 2 work near the Metro station was set to resume post-monsoon, with calls for Metro to increase coach numbers

<p><strong>ESCALATORS OPENED</strong></p>
<p>July 5, 2024: Two of six escalators in the east circulating area were <a href="https://www.mid-day.com/mumbai/mumbai-news/article/mumbai-two-escalators-at-ghatkopar-station-opened-23360413?entertainment-bollywood-news-article-breakingnews">inaugrated</a>, providing access to new FOB. The full upgrade, including multiple bridges and decks, was expected to be completed by December 2026</p>

10/13

ESCALATORS OPENED

July 5, 2024: Two of six escalators in the east circulating area were inaugrated, providing access to new FOB. The full upgrade, including multiple bridges and decks, was expected to be completed by December 2026

<p><strong>SLOW PROGRESS QUESTIONED</strong></p>
<p>July 12, 2024: <a href="https://www.mid-day.com/mumbai/mumbai-news/article/mumbai-blueprint-for-two-year-ghatkopar-station-upgrade-23363029">MRVC plans</a> two phases with new FOBs and decks, noting that a five-minute Metro delay can add nearly 2,000 commuters. Completion is targeted for 2027</p>

11/13

SLOW PROGRESS QUESTIONED

July 12, 2024: MRVC plans two phases with new FOBs and decks, noting that a five-minute Metro delay can add nearly 2,000 commuters. Completion is targeted for 2027

<p><strong>DEBRIS AND BARRICADES CAUSE RISKS</strong></p>
<p>February 14, 2025: Phase 2 work left debris and barricades on Platform 1, raising safety concerns. MRVC said it is speeding up foundation work and <a href="https://www.mid-day.com/mumbai/mumbai-news/article/ghatkopar-station-upgrade-turns-risky-as-debris-chokes-platform-23483232">debris</a> clearance, with completion still targeted for 2027</p>

12/13

DEBRIS AND BARRICADES CAUSE RISKS

February 14, 2025: Phase 2 work left debris and barricades on Platform 1, raising safety concerns. MRVC said it is speeding up foundation work and debris clearance, with completion still targeted for 2027

<p>The flooring work of the new wide bridge is underway at the CSMT-end. The new bridge is adjacent to the BMC skywalk abutting the Metro station&nbsp;</p>

13/13

The flooring work of the new wide bridge is underway at the CSMT-end. The new bridge is adjacent to the BMC skywalk abutting the Metro station 

Photo of Day

Breaking barriers and building pyramids — Women power in action!

Breaking barriers and building pyramids — Women power in action!

Sashastra Seema Bal’s (SSB) Daredevils team performs during rehearsals for the Republic Day Parade, in New Delhi. PIC/PTI

Advertisement