Mumbai: Section of Gokhale bridge may be opened by Feb-end

A portion of the bridge is being concreted

Listen to this article :
Concreting work being carried out on a section of bridge. Pic/Anurag Ahire

Concreting work being carried out on a section of bridge. Pic/Anurag Ahire

The Gokhale bridge construction is nearing completion, and the Brihanmumbai Municipal Corporation (BMC) plans to commence asphalt work on the railway portion next week. A section of the bridge is expected to be open by the end of the month.

“Concrete has been applied to a section of the bridge, and following the guidelines, a 21-day curing period is required for the concrete road. Once the curing is completed next week, we will proceed with asphalting on the railway track portion to allow vehicles to pass on the newly constructed approach road,” said a BMC official working on the project.

Buy now to read the full story.

For just ₹/-

Already a member? Login

For any queries please contact us: E-mail: support@mid-day.com

Trending Stories

Latest Photoscta-pos

Latest VideosView All

Latest Web StoriesView All

Mid-Day FastView All

Advertisement