19 December,2022 08:29 PM IST | Mumbai | Ranjeet Jadhav
Pic/MMRDA
The first part of central obligatory span of Flyover number 2 in Mankhurd-Thane direction of Chhedanagar Junction flyover was successfully launched on Monday morning.
The central obligatory span is quite crucial and difficult as it is in curved shape. This span is being constructed at level 2, above the existing flyover at Eastern express highway. The 202 meter obligatory span is split into 6 parts, are being constructed with structural steel. The total weight of this girders are around 890 MT.
Also Read: There should not be any politics: Eknath Shinde on Maha-Karnataka border issue
The span which was launched is one out of 6. This span is combination of 3 girders, which is 31 meter long and 2 meters each in height, weigh is around 110 MT.
ALSO READ
Indian Army arrests Lashkar-e-Taiba group guide in Poonch dst of Jammu-Kashmir
"Sanjay Raut speaks same as Pakistan and ISI": Shiv Sena MP Naresh Mhaske over UBT leader's remarks on Pahalgam attack
Case filed against Jitendra Awhad for misleading people on Ladki Bahin Yojana
Ajit Pawar-led NCP to contest MLC election from Mumbai Teachers constituency
Karnataka results won't affect Lok Sabha, Maharashtra elections: CM Shinde
"The work of Chheda Nagar junction improvement project is fast progressing. With all girders fabricated in Hyderabad have already arrived at the site, are now being assembled. The remaining parts are planned to launched within next 20 days," said S.V.R. Srinivas, Metropolitan Commisione, MMRDA.