22 July,2018 04:45 PM IST | Mumbai | Ranjeet Jadhav
In order to expedite the metro construction work in the Dahisar-DN Nagar metro corridor stretch that passes through New Link Road, authorities have imposed six-hour traffic blocks in the night, between midnight and 6 am. Commuters are being diverted to another route.
An official from MMRDA said, "We want to complete the civil work of the Dahisar-Andheri East metro line 2A at the earliest and hence, we are blocking traffic at some locations on New Link Road at the spots where the girder launching has to be done." This block will continue for two to three months, officials said.
According to the status report by MMRDA, 58 per cent work of the piers along the alignment is already complete. Besides that, work on 17 metro stations is also in progress. A total of 510 girders have been erected, out of the 1,435.
MMRDA had approached the traffic police department to get permission for the traffic blocks. "The work of girder launching is done only at night as it is not possible to get that done during the day. In the night, when traffic movement is low, there should be no problem caused by the diversion or closure of one section of the road," added the MMRDA official.
ALSO READ
Ganeshotsav 2024: 5 famous Ganpati pandals one must visit in Mumbai this year
Mumbai: Gokhale bridge second girder finally launched, lowering to begin soon
BMC completes transfer of girder from southern side of Gokhale Bridge
This restaurant in Andheri serves food from Himachal Pradesh, Nepal, China
Dating app scam probe: Two city clubs get notices for duping men on dating apps
58%
Pier work is already complete
Catch up on all the latest Crime, National, International and Hatke news here. Also download the new mid-day Android and iOS apps to get latest updates